2004 America Project
Updated 09-09-04
The NPS has approved our plan.
The GLSPS is planning
to repair some damage that has occurred in the last two years to the America. The park
reviewed the proposed plan and has approved it. The project is planned for September
10-12, a Friday through Sunday.
The work will be done using three boats the Heyboy,
Amarada, and RLT Diver III.
In
an attempt to use the web to do the project sign-ups I am posting the list of
positions and personnel signed up. Members
who have work experience will be given preference for the main tasks.
Members who have taken the training classes will be given preference for
the apprentice positions. Members who
applied last year but were turned down for space reasons are on the top of the
list. We always try to
have 25% new workers. Current
First Aid and CPR certification is a strong plus.
To sign up email me at kmerryman@glsps.org
and let me know what position you would like to be considered for and what your
background and training is.
America Project Position Descriptions
|
Tentative Position |
# Needed - Names |
# Needed - Apprentices |
|
Project Manager |
1 - Ken Merryman |
|
|
Task Manager |
2 -Steve Daniel |
|
|
Safety Officer |
1 - Phil Kerber |
1 - |
|
Boat Captains |
2 - Ken Merryman |
N/A |
Scuba Dive Team #1 |
4- Ken Merryman |
2
- Jerry
Erdman |
|
Tenders – Scuba Team #1 |
3-4- Same |
|
Scuba Dive Team #2 |
4- Steve Daniel |
|
|
Tenders – Scuba Team #2 |
4 - Same |
|
Scuba Dive Team #3 |
4- Ron Johnson |
|
|
Tenders – Scuba Team #3 |
4 - Same |
|
|
Cook |
1 - Bob Nelson |
1 - |
|
Machinery Operator |
1 - Ken Knutson |
1 - Bill Wallace |
|
Craftsman |
2 - Ken Knutson |
|
|
Quarter Master |
1 - Tom Brueshaber |
N/A |
|
Deck Hand/Gopher |
Everyone at a time |
N/A |
| Photographer/ Documenter |
Al Brown, Joe Schambers |
2004 Repair Tasks
This year's project will be a short focused set of tasks. We only had a couple of weeks to plan it so keeping it simple was important. Basically we will have one full work day and a setup and teardown day. This years tasks will be the following:
1. Re-install the open afterdeck pillars that fell down sometime in the last three years.
2. Move and refasten the aft wall of the upper engine room that shifted to port this year.
3. Stabilize the tables in the dining room.
4. Do a Zebra Mussel video survey of the Windigo Dock and Beaver Is Dock.
5. Stabilize the purser's office wall and mailboxes in the pursers office that have fallen down.
6. Re-assemble the port side grand staircase lower newel post.
7. Fix mooring. The park mooring block is upside-down again. We will right it with our lift bag.